Ufficio federale delle strade USTRA
A2 Secondo tubo San Gottardo

16.9 km

in lenght 

14.173km

excavation with tunnel boring machines

7.4 million

tonnes of excavated material

13.5 m

per working day – advance rate in front of the fault zone

10 years

construction period

2.14 billion

project costs

20.3 m

per working day – advance rate after the fault zone

620'000 m2

installation area